PROJECT
The design process can take approximately 10-15 days. After approval is obtained, the following steps are taken:
- Placing orders for materials
- Providing single parts (preparing for drilling, cutting)
- Preparing manufacturing drawings
- Preparing assembly drawings
MATERIAL
After the contract is signed:
- A material list is obtained from the 3D model, and orders are placed accordingly.
- Once the ordered materials are procured, they are sent for sandblasting.
- After Sa2.5 sandblasting is completed, a shop primer (15-20 microns) is applied to prevent surface rust, and the materials are sent to the workshop.
- This process typically takes around 10-15 days.
PRELIMINARY
The work program is published to relevant units.
- Plate and profile cutting lists are prepared.
PRODUCTION
According to the lists:
- Procurement of plates and profiles
- Drilling of holes
- Manufacturing of columns, beams, and cross connections in priority order according to the work program.
|
|